Internation Internet Cafe

Company: Joyes Inc.
Manager: Nathan Joyes
Start: January 15, 2007
Finish: May 3, 2007
Report Date: February 25, 2007

Gantt Chart

Week 4, 2007 Week 5, 2007 Week 6, 2007 Week 7, 2007 Week 8, 2007 Week 9, 2007 Week 10, 2007 Week 11, 2007 Week 12, 2007 Week 13, 2007 Week 14, 2007 Week 15, 2007 Week 16, 2007 Week 17, 2007 Week 18, 2007
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3

Tasks

WBS Name Start Finish Work Priority Complete Cost Notes
1 Phase I Jan 15 Jan 15
2 Define the Application Objectives and Scope Jan 15 Jan 16 4d
2.1 Project Charter Jan 15 Jan 16 2d 100%
2.2 Project Plan Jan 15 Jan 16 2d 100%
3 Detailed System Investigation Jan 17 Jan 17 1d
3.1 Summarize 'Client' Interviews Jan 17 Jan 17 1d 100% Since there is no real client, this task details the creation of a document that fully describes what the 'client' was looking for, as well as other details required to complete the project.
4 Modeling and Analysis Jan 18 Feb 2 21d
4.1 Use Case Diagram Jan 18 Jan 19 2d 100%
4.2 Use Case Description Jan 18 Jan 26 7d 100%
4.3 Class Diagram Jan 29 Jan 30 2d 100% This is the analysis level class diagram
4.4 State Chart Diagrams Jan 29 Feb 2 5d 100%
4.5 Sequence Diagrams Jan 29 Feb 2 5d 100%
5 System/Subsystem Design Feb 5 Feb 9 10d
5.1 Package Diagram Feb 5 Feb 6 2d 100%
5.2 Class Diagram Feb 5 Feb 7 3d 100% This is the design level class diagram
5.3 Network Model Feb 5 Feb 9 5d 100%
6 Database Design Feb 5 Feb 9 10d
6.1 Database ERD Feb 5 Feb 9 5d 100%
6.2 Data Dictionary Feb 5 Feb 9 5d 100%
7 Screen/Report Design Feb 5 Feb 9 10d
7.1 User Interface Layout Feb 5 Feb 9 5d 100%
7.2 Navigation Diagram Feb 5 Feb 9 5d 100%
8 Phase II Feb 9 Feb 9
9 Prepare Detailed Design Plan Feb 12 Feb 22 20d
9.1 Project Plan Feb 12 Feb 13 2d 100% Review the project plan now that the project is well underway.
9.2 Screen Prototypes Feb 12 Feb 22 9d 100%
9.3 Report Design Feb 12 Feb 22 9d 100%
10 Present Project Plan to Faculty Advisor Feb 23 Feb 23 1d
10.1 Formal Presentation Feb 23 Feb 23 1d 100%
11 Present Project Plan to Client Feb 26 Feb 26 1d
11.1 Client Revisions Feb 26 Feb 26 1d 50% Since there is no 'Client' this task is for review of the product to make sure it matches the initial 'Client' interviews.
12 Phase III Feb 26 Feb 26
13 Code Programs and Test Feb 27 Mar 29 35d
13.1 Project Plan Feb 27 Feb 28 2d 100% Again further review of the project plan is necessary at the start of this phase.
13.2 Unit Test Plans Feb 27 Mar 5 5d 50%
13.3 Module Test Plans Feb 27 Mar 5 5d 0%
13.4 Code Programs Mar 6 Mar 26 15d 0%
13.5 Unit Test Plan Results Mar 6 Mar 12 5d 0%
13.6 Individually Test Modules Mar 27 Mar 29 3d 0%
14 Phase IV Mar 29 Mar 29
15 Assemble Modules to Make the System Mar 30 Apr 12 24d
15.1 Integration Tests and Results Mar 30 Apr 6 6d 0%
15.2 Help/Tutorial Mar 30 Apr 6 6d 0%
15.3 Deployment Guides Apr 9 Apr 12 12d
15.3.1 System Administrator Apr 9 Apr 12 4d 0%
15.3.2 User Apr 9 Apr 12 4d 0%
15.3.3 Standalone Installation Apr 9 Apr 12 4d 0%
16 Phase V Apr 12 Apr 12
17 Public Demonstration and Marking Apr 13 May 3 17d
17.1 System Documentation Apr 13 Apr 19 5d 0%
17.2 User Manuals Apr 13 Apr 19 5d 0%
17.3 ID Sheet and Installation CD Apr 13 Apr 19 5d 0%
17.4 Final Testing by Advisor Apr 25 Apr 25 1d 0%
17.5 Tech@Work Day May 3 May 3 1d 0%

Resources

Name Short name Type Group Email Cost